CROM Tanks Capture and Store Wastewater During Heavy Rainfall
CROM is a key partner in Chattanooga’s largest design-build water infrastructure initiative, known as the e2i2 (Environmental and Economic Infrastructure Improvements) Project. An element of “Clear Chattanooga,” the city’s sewer overflow abatement program, e2i2 is designed to capture and store excess wastewater during heavy rainfall events to mitigate sewer overflows, improve regional environmental quality and accommodate the city’s future growth and development.
Tanks Total
CROM designed and built three prestressed concrete tanks across two jobs sites—two tanks in west Chattanooga and one in South Lee Highway. Combined, the tanks will hold 40 million gallons of wet-weather wastewater–enough to fill more than 60 Olympic-size swimming pools.
The e2i2 Project leverages CROM’s progressive design-build model, which brings design and construction teams together to develop the solution collaboratively rather than completing design in isolation before construction begins.
The construction phase of the project began in 2025, with structural completion targeted for March 2027 and full operation expected by June 2027.