Time Lapse of Prestressed Concrete Tank Construction at Kennedy Space Center

Structural Integrity

Minimal Maintenance

Exceeds Standards

PE Certified

Prestressed Concrete Tank Applications

Phases Prestressed Concrete Tank Construction

CROM Phases Prestressed Concrete Tank Construction Casting the Floor
01

Casting the Floor

The foundation of the prestressed tank is typically a heavily reinforced thin membrane concrete slab. Structural and ballast floor designs are also common, depending on site condition requirements.

CROM Phases Prestressed Concrete Tank Construction Galvanized steel shell diaphragm
02

Diaphragm

Galvanized steel shell diaphragm is erected on a system of formwork specially designed for this purpose. The steel shell extends the full height of the tank to ensure watertightness. Vertical joints in the steel shell are sealed watertight by epoxy injection.* U.S. Patent No. 5,150,551

CROM Phases Prestressed Concrete Tank Construction Outside Core Wall
03

Outside Core Wall

Exterior encasement of the steel shell is accomplished with shotcrete, which is pneumatically placed concrete. The core wall of the tank is constructed using successive layers of shotcrete until the required wall thickness is achieved.

CROM Phases Prestressed Concrete Tank Construction Inside Core Wall
04

Inside Core Wall

After the formwork system is removed from the tank interior, shotcrete is applied to encase the diaphragm and complete the interior core wall.

CROM Phases Prestressed Concrete Tank Construction Dome Shell Forming & Casting
05

Dome Shell Forming & Casting

The free-span concrete dome roof is made possible with the aid of a forming system that ensures accurate dome curvature. The free-span dome roof is then constructed of cast-in-place concrete.

CROM Phases Prestressed Concrete Tank Construction Prestressing
06

Prestressing

Both the core wall and dome ring band are circumferentially prestressed using high-strength steel wire wrapped around the tank in a continuous helix. To avoid over-stressing or under-stressing of the tank, wire tension is measured via an electronic digital stressometer applied to the tank wall.

CROM Phases Prestressed Concrete Tank Construction Shotcrete Overcoat
07

Shotcrete Overcoat

To protect the prestressing elements, a shotcrete covercoat is applied to the exterior, which permanently bonds the wire to the tank wall. The covercoat completes the concrete portion of the tank construction.

CROM Phases Prestressed Concrete Tank Construction Tank Accessories
08

Tank Accessories

The final stage of construction involves installation of accessories and if desired, application of exterior coatings for decorative purposes.

Let’s Build Something for Life

For infrastructure that’s built to last, choose a partner that supports its entire life.
CROM, your lifecycle partner.